High Court rejects Govt appeal over Rs 57 lakh contractor payout

Rules delayed deposit can’t revive defense rights in MLA Hostel electrical suit

HC upholds eviction from migrant property

Kashmir Impulse Desk

Srinagar, Nov 14

The High Court of Jammu and Kashmir and Ladakh has dismissed a government appeal against a lower court order directing it to pay over Rs 57 lakh plus interest to contractors for electrical work executed at Srinagar’s MLA Hostel in 2019 and 2020.

Justice Moksha Khajuria Kazmi upheld an August 12, 2023 decree by the Additional District Judge in Srinagar, ruling that the administration forfeited its right to contest the recovery suit by failing to meet a court-ordered deposit deadline.

Contractors had sought Rs 57.3 lakh for work carried out on official instructions, including Rs 18.4 lakh worth of installations ordered verbally by the Srinagar District Magistrate in 2019 to house political leaders detained at the hostel following the revocation of Article 370.

In December 2022, the trial court granted the government conditional leave to defend the summary suit under Order XXXVII of the Code of Civil Procedure, provided it deposited Rs 37.8 lakh and filed a written defence within 30 days.

The administration deposited Rs 19 lakh in March 2023 – missing the deadline – and paid the remaining Rs 18.8 lakh in July 2025, nearly two years after the final decree was issued.

A separate government challenge to the conditional deposit order had already been dismissed in May 2023.

In rejecting the appeal, Justice Kazmi held that paying the balance nearly two years post-judgment could not retroactively restore defence rights, noting the government offered no valid explanation for the delay.